Legislation Details

File #: 26-0301    Version: 1 Name: Davis Rd, 15-inch Gravity Sewer Replacement (WW1801K)
Type: Agenda Item Status: Approved
File created: 7/27/2026 In control: Capital Projects
On agenda: 8/11/2026 Final action: 8/11/2026
Title: Consider and take action on a resolution authorizing a construction contract with Ram Rod Utilities, LLC for the Davis Road 15-Inch Gravity Sewer Replacement Project (WW1801K) in an amount not to exceed $378,535.00 and authorizing an additional $37,853.00 for a Work Change Directive budget for a total construction budget of $416,388.00 (Executive Director of Capital Projects)
Attachments: 1. Proposed Resolution, 2. Exhibit A - Construction Contract Agreement, 3. Letter of Recommendation and Bid Tabulation, 4. Project Layout, 5. CIP Project Sheet, 6. CIP Aerial Map (Modif.)

Title

Consider and take action on a resolution authorizing a construction contract with Ram Rod Utilities, LLC for the Davis Road 15-Inch Gravity Sewer Replacement Project (WW1801K) in an amount not to exceed $378,535.00 and authorizing an additional $37,853.00 for a Work Change Directive budget for a total construction budget of $416,388.00 (Executive Director of Capital Projects)

 

Background:

Approval of this resolution will authorize the award of a construction contract with Ram Rod Utilities, LLC, for the Davis Road 15-Inch Gravity Sewer Replacement Project (WW1801K) in an amount not to exceed $378,535.00 and authorizing an additional $37,853.00 for a Work Change Directive budget for a total construction budget of $416,388.00.

 

The project scope is to replace approximately 550 linear feet of existing 15-inch gravity sewer along Davis Road near the City’s Davis Road Lift Station using pipe-bursting and open-cut construction methods. Work includes excavation, bypass pumping, appurtenances, coatings, tie-ins, connection to the existing wet well, and all other work necessary to place the replacement gravity sewer into service.   The project also includes rehabilitation of three (3) existing 5-foot-diameter sanitary sewer manholes.

 

Three (3) sealed bids for the project were received on July 20, 2026 (Bid No. 2026-044).  Based on the City’s A+B bidding method and bids and contract times received, Ram Rod Utilities, LLC submitted the lowest responsible and responsive cost value bid in amount of $378,535.00 and 105 calendar days.  Attached is the City’s engineering consultant’s recommendation of award and bid tabulation.

 

 

Attachments:

1.                     Proposed Resolution

2.                     Exhibit A - Construction Contract Agreement

3.                     Letter of Recommendation and Bid Tabulation

4.                     Project Layout

5.                     CIP Project Sheet

6.                     CIP Aerial Map (Modif.)

 

                                     

FUNDING

{X} Funding in the amount of $416,388 is available from Miscellaneous Utility Capital Projects Fund, fund 1055, with expenses charged to project expense string WW1801K- CONSTRUCT- CONSTRUCT -RS CASH.

 

 

STRATEGIC PLANNING

{X} Addresses Strategic Planning Critical Success Factor #1: Develop and Maintain our Infrastructure.