Skip to main content
File #: 19-0641    Version: 1 Name: ST1912 SSH FS 6 Median Cut Teamwork construction award
Type: Agenda Item Status: Approved
File created: 11/8/2019 In control: City Council
On agenda: 11/19/2019 Final action: 11/19/2019
Title: Consider and take action on a resolution: 1) authorizing a construction contract with Teamwork Construction Services for the SSH/SH96 Right-turn-lane & SSH Fire Station 6 Median Cut (ST1912) in an amount not to exceed $376,956.74 and 2) authorizing an additional $37,696 for a construction work change directive budget for a total construction budget of $414,652.74 (Director of Budget & Project Management)
Attachments: 1. Data Sheet, 2. Proposed Resolution, 3. Exhibit A - Agreement with Teamwork Construction Services, 4. Recommendation Letter & Bid Tab, 5. CIP project sheet, 6. Aerial Map

Title

Consider and take action on a resolution: 1) authorizing a construction contract with Teamwork Construction Services for the SSH/SH96 Right-turn-lane & SSH Fire Station 6 Median Cut (ST1912) in an amount not to exceed $376,956.74 and 2) authorizing an additional $37,696 for a construction work change directive budget for a total construction budget of $414,652.74 (Director of Budget & Project Management)

 

 

Background:

Approval of this resolution will authorize the award of the construction contract to Teamwork Construction Services for the construction of the SSH/SH96 RTL & SSH FS6 Median Cut Project (ST1912) and authorize funds for a construction work change directive budget.

 

This project will extend the right-hand turning lane northbound on South Shore Harbor Boulevard that turns to eastbound onto State Highway 96; as well as provide a median cut with a southbound left turn lane for entry/exit of fire trucks at Fire Station No. 6 on South Shore Boulevard.

 

The project also includes:

 

1.                     Installation of two (2) traffic warning signal lights, with power source, to alert oncoming traffic to stop so that fire trucks may enter/exit the fire station safely in emergency and non-emergency situations

2.                     Add an underground transformer on the west side of the median as a power source for the signal lights

3.                     Extending the right-hand turning lane northbound on SSH Blvd to eastbound on SH96

4.                     Add a control function inside Fire Station #6 that controls the signal lights

 

There are two (2) sealed bids for this project that were received on Tuesday, October 29, 2019 (Bid No. 19-CIP-041). Teamwork Construction Services submitted the lowest bid, based on the A+B bidding system, in the amount of $376,956.74 and for a construction time of 120 calendar days. Attached is the City's engineering consultant's recommendation of award, along with the bid tabulation.

 

Staff requests the approval of the award of the construction contract and authorization of funds, as

follows:

1. Construction contract with Teamwork Construction Services in the amount of $376,956.74.

2. Establish a construction work change directive budget in the amount of $37,696 (10% of construction amount) that will allow staff to approve minor field changes (up to $50,000) to expedite decisions and avoid possible construction delays and/or damage claims by the contractor.  Construction material testing services will be funded from the contingency.

 

This project is anticipated to take 120 calendar days from the notice to proceed.

 

 

 

Attachments:

1.                     Data Sheet

2.                     Proposed Resolution

3.                     Exhibit A - Agreement with Teamwork Construction Services

4.                     Letter of Recommendation with Bid Tab

5.                     CIP Project Sheet

6.                     Aerial Map

 

CONTRACT ORIGINATION: Construction Contract with Teamwork Construction Services has been reviewed and approved by City Attorney's office

               

FUNDING

{X} Funding in the amount of $414,653 is available from 2018 CO fund 5245 with expenses charged to project expense string ST1912-CONSTRUCT-CONSTRUCT - 2018 CO

 

STRATEGIC PLANNING

{X} NOT APPLICABLE