Legislation Details

File #: 26-0365    Version: 1 Name: FY2026 BA Capital Purchase Accrosports
Type: Agenda Item Status: First Reading
File created: 8/26/2026 In control: Budget
On agenda: 9/8/2026 Final action:
Title: Consider and take action on an ordinance amending the City of League City, Texas, Governmental, Proprietary, and Capital Funds Budget for Fiscal Year 2026 by amending Ordinance No. 2025-31, Ordinance No. 2026-08, and Ordinance No. 2026-18 to adjust the operating and capital budget for actual and projected expenditures (Assistant City Manager - CFO) Staff requests approval on first and final reading. Taxpayer Impact Statement Required per H.B. 1522 effective September 1, 2025 for TY2024 (FY2025) and TY2025 (FY2026) 2024 Adopted Tax Rate $0.369 with average homestead taxable value of $351,138 equals tax of $1,295.70 2025 No-New-Revenue Tax Rate $0.36355 with average homestead taxable value of $362,634 equals tax of $1,318.36 2025 Proposed Tax Rate $0.36355 with average homestead taxable value of $362,634 equals tax of $1,318.36
Attachments: 1. Proposed Ordinance with Exhibits A, B & C, 2. New City Facility Funding
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Consider and take action on an ordinance amending the City of League City, Texas, Governmental, Proprietary, and Capital Funds Budget for Fiscal Year 2026 by amending Ordinance No. 2025-31, Ordinance No. 2026-08, and Ordinance No. 2026-18 to adjust the operating and capital budget for actual and projected expenditures (Assistant City Manager - CFO)

Staff requests approval on first and final reading.

 

Taxpayer Impact Statement Required per H.B. 1522 effective September 1, 2025 for TY2024 (FY2025) and TY2025 (FY2026)

2024 Adopted Tax Rate $0.369 with average homestead taxable value of $351,138 equals tax of $1,295.70

2025 No-New-Revenue Tax Rate $0.36355 with average homestead taxable value of $362,634 equals tax of $1,318.36

2025 Proposed Tax Rate $0.36355 with average homestead taxable value of $362,634 equals tax of $1,318.36

 

Background

 

The proposed ordinance requests an increase to the Capital Budget to add project, Fire Administration & Police Training Center, as shown on Exhibit B ($6,000,000) for the purchase of the building located at 2705 Dickinson Avenue S (Acrosports Kid Center) in the amount of $4,000,0000 and $1,500,000 for renovations to transition the open space to a designated Fire Administration and a Police Training Center. An additional $500,000 will be budgeted for project contingency.

 

If approved, the proposed ordinance would amend the City’s FY2026 Capital Budget to incorporate proposed adjustments for the following:

 

 

CAPITAL BUDGET - EXHIBIT B

 

Formally add Fire Administration & Police Training Center as a project to the Capital Budget with a budget of $6,000,000.

 

FUNDING

 

                     Transfer $3,000,000 in unencumbered TIRZ 2 funds, fund 2615, ($1,500,000) in funding from Alamo Draft House and an additional ($1,500,000) in uncommitted TIRZ 2 funds to fund 5015 Miscellaneous Capital Projects Fund in the CIP.

                     $2,085,000 Budgeted in FY2027 in Miscellaneous Capital Projects Fund, fund 5015, for the construction of the Multi-Function Training Facility is being brought forward to fund the purchase and renovations of the new Fire Administration and Police Training Center in FY2026. The Multi-Function Training Facility will be omitted in FY2027 1st QTR Budget Amendment.

                     $915,000 will be added to the Capital Budget from Fire Station 7 funds, fund 5018.

                     With the approval of the Fire Administration and Police Training Center the FY2026 Amended Capital Budget increases from $331,188,766 to $339,041,876.

 

In addition to the data sheet this packet includes:

 

                     Proposed Budget Ordinance and Exhibit A, B, C, and Funding Plan for the New Facility - Exhibit A (No change); Exhibit B details the Capital Budget; Exhibit C details the citywide summary.

                     The Funding Plan for the New Facility is the financial breakdown of how the city intends to finance the purchase and renovations of the proposed Fire Administration & Police Training Center. 

 

 

FUNDING

{X} Funds are available from CIP Capital Projects and TIRZ 2.

 

STRATEGIC PLANNING

{X} NOT APPLICABLE