File #: 24-0168    Version: 1 Name: Bay Colony 14-15 FM to SWWRF (WW2301)
Type: Agenda Item Status: Approved
File created: 3/26/2024 In control: Capital Projects
On agenda: 5/14/2024 Final action: 5/14/2024
Title: Consider and take action on a resolution authorizing a professional services agreement with DE Corporation A Part of Gannett Fleming for the design, bid and award, and construction phase services related to the Re-route 18-inch Bay Colony MUD 14-15 Force Main to SWWRF Project (WW2301), in an amount not to exceed $295,060 (Executive Director of Capital Projects)
Attachments: 1. Proposed Resolution, 2. Exhibit A - PSA with Proposal, 3. CIP Project Sheet, 4. CIP Aerial Map(Modif.), 5. Vendor Report Card

Title

Consider and take action on a resolution authorizing a professional services agreement with DE Corporation A Part of Gannett Fleming for the design, bid and award, and construction phase services related to the Re-route 18-inch Bay Colony MUD 14-15 Force Main to SWWRF Project (WW2301), in an amount not to exceed $295,060 (Executive Director of Capital Projects)

 

Background:

Approval of this resolution will authorize a professional services agreement with DE Corporation A Part of Gannett Fleming for the  design, bid and award, and construction phase services related to the re-routing of 18-inch Bay Colony MUD 14-15 Force Main from Calder Road to a gravity trunk sewer at end of Grand Bargain’s sanitary sewer system to convey flow to Southwest Water Reclamation Facility (SWWRF) (WW2301). 

 

Currently, the 18-inch force main extends from Bay Colony MUD 14-15 lift station to 36” gravity sewer line near Ervin Road which then flows north to the Dallas Salmon Wastewater Treatment Plant.  Based on the adopted wastewater Master Plan, this flow was to be diverted to the SWWRF once the Grand Bargain’s trunk sewer system is in place.  This diversion will include approximately 9,000 feet of new 18-inch force main, control valves and some length of large gravity sewer line.  Project will also need to include pumps and controls upgrades at the Bay Colony MUD 14-15 lift station to convey the flow to new location.    

 

Final design phase is proposed to be complete in 240 days. The estimated construction cost is $3,000,000 and will be reprogrammed in the FY2025 for construction. The original estimated cost estimate was $1,370,200, but due to material shortage and demand, the cost of materials has increased.

 

Consultant has submitted a proposal to perform Design, Bid & Award and Construction Phase services for a budget not to exceed $295,060, which includes is the following major services categories and fees:

 

Total Basic Engineering Services                                                                                                                     238,500

 

Total Special Services                                                                                                                                               $  56,560

 

GRAND TOTAL BASIC & SPECIAL SERVICES                                                     $ 295,060

 

Design phase is proposed be completed within 240 days, excluding City review periods, followed by bid and construction phases.

 

Attachments:

 

1.                     Proposed Resolution

2.                     Exhibit A - PSA with Proposal

3.                     CIP Project Sheet

4.                     CIP Aerial Map (Modify)

5.                     Vendor Report Card

 

FUNDING 

{X} Funding in the amount of $295,060 is available from Wastewater Capital Recovery Fees, Fund 1045, with expenses charged to project expense string WW2301-PLAN DESIGN - DESIGN - WWCRF.