Title
Consider and take action on a resolution authorizing a construction contract with Teamwork Construction Services, Inc. for the League City Parkway Right Turn Lane - Calder Road to Butler Road (ST2004) in an amount not to exceed $1,411,319.50, authorizing a Work Change Directive budget of $141,132, and authorizing a contract with Geotech Engineering & Testing for materials testing in an amount not to exceed $17,267, for a total construction budget of $1,569,718.50 (Executive Director of Capital Projects)
Background:
Approval of this resolution will authorize the award of a construction contract with Teamwork Construction Services, Inc. for the League City Parkway Right Turn Lane - Calder Road to Butler Road (ST2004) in an amount not to exceed $1,411,319.50, authorizing a Work Change Directive budget of $141,132, and authorizing a contract with Geotech Engineering & Testing for materials testing in an amount not to exceed $17,267, for a total construction budget of $1,569,718.50 (Executive Director of Capital Projects)
The project includes the completion of an extra lane (third lane) to the League City Parkway, starting from approximately 450 feet of Butler Road to approximately 400 feet eastbound of Calder Road, near IH 45 Feeder Road (This will provide a continuous 3rd lane from just west of Hobbs Road to I-45). The scope of work includes the construction of a 12-foot-wide lane, associated pavement widening, traffic signal modifications, sidewalk and intersection improvements, S-median reconfiguration at Calder Road, and some utility adjustments. The project also incorporates stormwater pollution prevention (SWPPP) measures, tree protection, curb inlet modifications, and traffic control measures to ensure safety and operational continuity during construction.
Five (5) sealed bids for the project were received on March 25, 2025 (Bid No. 25-015). One bidder was disqualified since the submitted proposal did not conform to the City’s General Instructions to Bidders criteria. Based on the City’s A+B bidding method, and bids and contract times received, Teamwork Construction Services, Inc. submitted the lowest responsible and responsive cost value bid in the amount of $1,411,319.50 and 180 calendar days to complete. The engineering consultant’s recommendation of the award and the bid tabulation are attached.
Attachments:
1. Proposed Resolution
2. Exhibit A1 - Teamwork Construction Contract
3. Exhibit A2 - Geotech Professional Services Agreement with Proposal - Material Testing
4. Letter of Recommendation and Bid Tabulation
5. General Project Layout
6. Galveston County Bond Nov 2017 Information
7. CIP Project Sheet
8. CIP Aerial Map
9. Vendor Report Card - Geotech Engineering & Testing.
FUNDING
{X} Funding in the amount of $1,569,718.50 is available from Galveston County’s 2017 Bond Issuance with expenses charged to project expense string ST2004-CONSTRUCT-CONSTRUCT-GALV CO. Expenses will be charged to fund 5015, Miscellaneous Capital Projects Fund, with reimbursement revenue deposited into the same fund.
Reimbursements for this project fall within the guidelines provided in the agreement with the County.
STRATEGIC PLANNING
{X} Addresses Strategic Planning Critical Success Factor #1: Develop and Maintain our Infrastructure.