File #: 25-0475    Version: 1 Name: Amendment -FM 270 Boat Ramp Improvements
Type: Agenda Item Status: Consent Agenda
File created: 9/30/2025 In control: Capital Projects
On agenda: 10/14/2025 Final action:
Title: Consider and take action on a resolution authorizing Amendment 4 to the Professional Services Agreement (PSA) with Burditt Consultants for the Planning and Design of the FM 270 Public Boat Ramp Renovations (PK1804) in an amount not to exceed $12,512 (Executive Director of Capital Projects)
Attachments: 1. Proposed Resolution, 2. Exhibit A - Amendment No. 4 with Proposal, 3. Original PSA with Burditt Consultants, 4. Approved Amendment No. 1, 5. Approved Amendment No. 2, 6. Approved Amendment No. 3, 7. CIP Project Sheet, 8. CIP Aerial Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Consider and take action on a resolution authorizing Amendment 4 to the Professional Services Agreement (PSA) with Burditt Consultants for the Planning and Design of the FM 270 Public Boat Ramp Renovations (PK1804) in an amount not to exceed $12,512 (Executive Director of Capital Projects)

 

Background:

Approval of this resolution will authorize Amendment 4 to the PSA with Burditt Consultants for the Planning and Design of the FM 270 Public Boat Ramp Renovations (PK1804) in an amount not to exceed $12,512. Amendment 4 when added to Amendment 2 and 3-previously approved administratively-equals $54,512, thus exceeding the City Manager approval level, requiring City Council approval.

 

Burditt Consultants (Burditt) and the City of League City (COLC) staff determined that Burditt is owed additional compensation based on a provision in the PSA that allows for an increase in the fee if the Opinion of Probable Cost (OPC) exceeds $500,000. In addition, COLC requested an updated OPC due to the time that has lapsed since the most recent OPC was provided by Burditt. The updated OPC is needed for the Boating Access Construction Grant application to the Texas Parks and Wildlife Department (TPWD) that COLC will submit soon to receive funding for the construction of this project.  This updated OPC will help the City substantiate the amount of construction grant which will be requested.  Planning and design phases of the project are completed and approved by TPWD and City was reimbursed $116,362.50 on October 3, 2025 as part of the grant for design services.     

 

The attached proposed Amendment 4 includes a fee increase of $12,512 for the following items:

-                     5% of fee for increased services in Final Design                            $2,378

-                     5% of fee for increased services in Bid/Award Phase                     $2,378

-                     10% of fee for increased services in Construction Observation      $4,756

-                     Provide up-to-date OPC as required by TPWD grant application    $3,000

Total Amendment 4 increase                                                       $12,512

 

Following is a more detailed explanation of the previous PSA and amendments:

 

Original PSA                                          $62,000: approved by City Council on 05/09/2018 (attached)

Amendment 1                      $93,000: approved by City Council on 10/09/2018 (attached)

Total PSA+A1          $155,000

 

Amendment 2                                          $31,000: approved administratively on 04/12/2019

Amendment 3                      $11,000: approved administratively on 11/02/2020

Amendment 4                      $12,512: proposed for approval by this Agenda Item

Total A2,3,4                                           $54,512

 

Original PSA ($62,000) - Covered preliminary design, and a construction estimate to allow a grant application to be submitted to Texas Parks and Wildlife Department (TPWD) for a combination of design and construction funding.

 

Amendment 1 ($93,000) - Provided for completion of all construction documents for the Boat Ramp Renovation project.

 

 

Amendment 2 ($31,000) - Provided for Burditt to A) conduct USACE permitting support activities consistent with project goals and B) Conduct Wetland Delineation.

 

Amendment 3 ($11,000) - Provided for Burditt to conduct 1) Hydraulic Impact Analysis, 2) carry out additional design services for developing construction documents, and 3) conduct regulatory work required by USFWS for the Boating Access Grant through TPWD.

 

Staff requests City Council approval of Amendment 4 as submitted by Burditt Consultants and reviewed by staff. 

 

 

Attachments:

 

1.                     Proposed Resolution

2.                     Exhibit A - Amendment No. 4 with Proposal

3.                     Original PSA with Burditt Consultants

4.                     Approved Amendment No. 1

5.                     Approved Amendment No. 2

6.                     Approved Amendment No. 3

7.                     CIP Project Sheet

8.                     CIP Aerial Map

                                     

FUNDING

{X} Funding in the amount of $12,512.00 is available from Park Dedication Fees, fund 5020, with expenses charged to project expense string PK1804-PLAN DESIGN- DESIGN-PARKS DED.

 

 

 

STRATEGIC PLANNING

    {X} Addresses Strategic Planning Critical Success Factor #3 Quality Community Amenities.