Legislation Details

File #: 26-0197    Version: 1 Name: 24" Water Line
Type: Agenda Item Status: Consent Agenda
File created: 5/12/2026 In control: Development Services
On agenda: 6/9/2026 Final action:
Title: Consider and take action on a resolution authorizing a Professional Services Agreement with GFT Infrastructure, Inc. in the amount of $345,000 for design, easement acquisition, bidding, and construction phase services associated with the extension of a 24-inch waterline along FM517 from approximately 900 feet west of Calder Road to approximately 700 feet east of Pedregal Boulevard (Executive Director of Development Services)
Attachments: 1. Proposed Resolution, 2. Professional Services Agreement - GFT Infrastructure, Inc., 3. CIP Project Sheet
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Consider and take action on a resolution authorizing a Professional Services Agreement with GFT Infrastructure, Inc. in the amount of $345,000 for design, easement acquisition, bidding, and construction phase services associated with the extension of a 24-inch waterline along FM517 from approximately 900 feet west of Calder Road to approximately 700 feet east of Pedregal Boulevard (Executive Director of Development Services)

 

Background:

Approval of this item will authorize the City Manager to execute a Professional Services Agreement (PSA) with GFT Infrastructure, Inc. (GFT) for engineering, surveying, easement acquisition, bidding, and construction administration services associated with the extension of a 24-inch waterline along FM517.

 

The proposed project will extend approximately 24-inch water transmission infrastructure along FM517 from approximately 900 feet west of Calder Road to approximately 700 feet east of Pedregal Boulevard. This project is intended to support long-term water distribution system capacity, reliability, and future growth in accordance with the City’s Master Water Plan and related capital improvement planning efforts.

 

GFT has provided a preliminary estimated construction cost of approximately $2,797,500 for the project plus easement acquisition costs.

 

The proposed scope of services includes:

                     Preparation of engineering design plans, specifications, and cost estimates for the proposed 24-inch waterline.

                     Coordination with TxDOT and acquisition of required permits for work within FM 517 right-of-way.

                     Easement acquisition support services, including surveying, metes and bounds descriptions, appraisals, negotiations, and acquisition coordination for approximately three easement parcels.

                     Bid phase support, including pre-bid meetings, addenda preparation, bid tabulation, and recommendation of award.

                     Construction phase services include shop drawing review, pay estimate review, construction coordination, substantial completion inspections, and record drawings.

 

The proposed PSA includes a total fee of $345,000 consisting of:

                     $285,950 in basic engineering services; and

                     $59,050 in special services associated with surveying, easement preparation, easement acquisition support, and project expenses.

 

The proposal anticipates approximately:

                     120 days for topographic survey, mapping, easement preparation, and 90% design submittals following receipt of right-of-access

                     30 days for final design following City review comments

                     60 days for bid and award activities

 

Construction duration is estimated at approximately 180 days.

 

Staff recommends approval of this agreement.

 

Attachments:

1. Resolution

2. Professional Services Agreement - GFT Infrastructure, Inc.

3. CIP Project Sheet

                                     

FUNDING

{ X }  Funding in the amount of $345,000 is available from Miscellaneous Utility Capital Projects Fund, fund 1055, with expenses charged to project expense string WT2601-PLAN DESIGN- DESIGN- RS CASH 

 

STRATEGIC PLANNING

{X}  Addresses Strategic Planning Critical Success Factor  # 1 -  Develop  &  Maintain our Infrastructure and Factor# 2- Financially Sustainable