File #: 26-0197    Version: 1 Name: 24" Water Line
Type: Agenda Item Status: Approved
File created: 5/12/2026 In control: Development Services
On agenda: 6/9/2026 Final action: 6/9/2026
Title: Consider and take action on a resolution authorizing a Professional Services Agreement with GFT Infrastructure, Inc. in the amount of $345,000 for design, easement acquisition, bidding, and construction phase services associated with the extension of a 24-inch waterline along FM517 from approximately 900 feet west of Calder Road to approximately 700 feet east of Pedregal Boulevard (Executive Director of Development Services)
Attachments: 1. Proposed Resolution, 2. Professional Services Agreement - GFT Infrastructure, Inc., 3. CIP Project Sheet

Title

Consider and take action on a resolution authorizing a Professional Services Agreement with GFT Infrastructure, Inc. in the amount of $345,000 for design, easement acquisition, bidding, and construction phase services associated with the extension of a 24-inch waterline along FM517 from approximately 900 feet west of Calder Road to approximately 700 feet east of Pedregal Boulevard (Executive Director of Development Services)

 

Background:

Approval of this item will authorize the City Manager to execute a Professional Services Agreement (PSA) with GFT Infrastructure, Inc. (GFT) for engineering, surveying, easement acquisition, bidding, and construction administration services associated with the extension of a 24-inch waterline along FM517.

 

The proposed project will extend approximately 24-inch water transmission infrastructure along FM517 from approximately 900 feet west of Calder Road to approximately 700 feet east of Pedregal Boulevard. This project is intended to support long-term water distribution system capacity, reliability, and future growth in accordance with the City’s Master Water Plan and related capital improvement planning efforts.

 

GFT has provided a preliminary estimated construction cost of approximately $2,797,500 for the project plus easement acquisition costs.

 

The proposed scope of services includes:

•                     Preparation of engineering design plans, specifications, and cost estimates for the proposed 24-inch waterline.

•                     Coordination with TxDOT and acquisition of required permits for work within FM 517 right-of-way.

•                     Easement acquisition support services, including surveying, metes and bounds descriptions, appraisals, negotiations, and acquisition coordination for approximately three easement parcels.

•                     Bid phase support, including pre-bid meetings, addenda preparation, bid tabulation, and recommendation of award.

•                     Construction phase services include shop drawing review, pay estimate review, construction coordination, substantial completion inspections, and record drawings.

 

The proposed PSA includes a total fee of $345,000 consisting of:

•                     $285,950 in basic engineering services; and

•                     $59,050 in special services associated with surveying, easement preparation, easement acquisition support, and project expenses.

 

The proposal anticipates approximately:

•                     120 days for topographic survey, mapping, easement preparation, and 90% design submittals following receipt of right-of-access

•                     30 days for final design following City review comments

•                     60 days for bid and award activities

 

Construction duration is estimated at approximately 180 days.

 

Staff recommends approval of this agreement.

 

Attachments:

1. Resolution

2. Professional Services Agreement - GFT Infrastructure, Inc.

3. CIP Project Sheet

                                     

FUNDING

{ X }  Funding in the amount of $345,000 is available from Miscellaneous Utility Capital Projects Fund, fund 1055, with expenses charged to project expense string WT2601-PLAN DESIGN- DESIGN- RS CASH 

 

STRATEGIC PLANNING

{X}  Addresses Strategic Planning Critical Success Factor  # 1 -  Develop  &  Maintain our Infrastructure and Factor# 2- Financially Sustainable