Title
Consider and take action on a resolution authorizing Change Order 3 to the construction contract with B&D Contractors for the Lobit Park Phase 1 Project (PK2206), in an amount not to exceed $69,517.75 (Executive Director of Capital Projects)
Background:
Approval of this resolution will authorize Change Order 3 to the construction contract with B&D Contractors, Inc for the Lobit Park Redevelopment Project Phase 1 (PK2206) in an amount not to exceed $69,517.75.
The purpose of this project is to continue to upgrade the City’s existing park facilities as outlined in the 2017 Parks, Trails, and Open Space Plan. The 27.54-acre Lobit Park was accepted in an interlocal agreement with the Galveston County on February 8, 2022, to be owned and operated by City of League City effective October 1, 2022.
The scope of work in this Phase 1 construction contract includes the following major upgrades/renovations:
1. Grading and resurfacing of the baseball infield and outfield playing surfaces to include irrigation.
2. Renovation of the baseball field amenities including new fencing, backstop, dugouts, bullpen areas, upgrades to the field lighting and connections for a new scoreboard.
3. Repairs to the pedestrian bridge at the northern pond.
4. Resurfacing the existing tennis court to provide 6 pickleball courts. It will include netting, perimeter fencing, lighting and access from the parking lot.
5. Upgrading the Park’s electrical system to include TNMP bringing 3-phase power service from approximately 3,000 feet away and installing a pad-mounted transformer in the Park. Contractor to tie in new system to the rest of the park amenities.
6. Bringing an 8-inch waterline from north of FM 646 into the Park to replace an old WCID water service coming from offsite.
7. General sidewalk improvements for connectivity around the baseball field and connection to the pickleball courts.
8. General site security lighting along the main driveway.
To date, 2 change orders have bee...