File #: 23-0355    Version: 1 Name: WCO CO1 Reytec Construction Inc.
Type: Agenda Item Status: Approved
File created: 7/31/2023 In control: Capital Projects
On agenda: 9/12/2023 Final action: 9/12/2023
Title: : Consider and take action on a resolution authorizing Change Order No. 1 to the construction contract with Reytec Construction, Inc. related to the 36-inch Waterline from State Highway 3 Booster Pump Station to the South Shore Harbour Booster Pump Station (WT1109) in a net amount not to exceed $112,449.78. (Executive Director of Capital Projects)
Attachments: 1. Data Sheet, 2. Proposed Resolution, 3. Exhibit A - Change Order No 1 and back up information, 4. Agenda Item 11F - 6-22-2021, 5. Contract 3220153
Title:
Consider and take action on a resolution authorizing Change Order No. 1 to the construction contract with Reytec Construction, Inc. related to the 36-inch Waterline from State Highway 3 Booster Pump Station to the South Shore Harbour Booster Pump Station (WT1109) in a net amount not to exceed $112,449.78. (Executive Director of Capital Projects)

Background:
Approval of this resolution will authorize the Change Order No. 1 in an amount not to exceed of $112,449.78 to the construction contract with Reytec Construction, Inc. related to the 36-inch Waterline from State Highway 3 Booster Pump Station to the South Shore Harbour Booster Pump Station (WT1109)

On June 22, 2021, Council authorized the award of the construction contract to Reytec Construction, Inc. for the installation of this 36-inch Waterline from State Highway 3 Booster Pump Station to the South Shore Harbour Booster Pump Station (Bid No. 21-CIP-032), for an amount not to exceed $20,176,170 and authorized an additional $2,017,617 for a Construction Work Change Directive (WCD)budget.

This project includes furnishing, installing, and providing all labor and materials required to install, approximately 17,730 linear feet of new 36-inch diameter potable water pipeline of which approximately 9,660 linear feet is by horizontal directional drill installation(fusible PVC pipe), approximately 1,995 linear feet of 36-inch diameter pipe inside 54-inch diameter steel casing installed by trenchless method, and approximately 6,075 linear feet by open-cut installation, including connections to the existing State Highway No. 3 Booster Pump Station and South Shore Harbour Booster Pump Station.

During the course of construction, project encountered major supply-chain issues including production and delivery of the fusible PVC pipe, deeper bore pits due to presence of deeper existing pipelines, discovery of new pipelines, and other unforeseen field conditions.

This agenda item presented to Council for the ...