Title
Consider and take action on an ordinance approving a Planned Unit Development (PUD) Amendment, PUD-25-0002 (Duncan PUD Amendment), to amend the Duncan PUD to permit 3-phase overhead power lines along Ervin Street, generally located north of Muldoon Parkway and west of Hobbs Road; subject to certain property owner commitments (Director of Planning)
The Planning and Zoning Commission recommended approval, 6-0-0, on February 12, 2026.
City Council postponed the item to the March 24, 2026 meeting, 7-1-0, on February 24, 2026.
Background:
Approval of this item will amend the Duncan PUD to allow overhead lines along Ervin Street.
Project Timeline:
January 22, 2019 - City Council adopted the Duncan PUD being 1,747.4 acres in size. The PUD consists of two separate developments, Samara to the north and Pedregal to the south.
November 28, 2023 - City Council adopted the first amended Duncan PUD, allowing specific lots within the Pedregal Development to a minimum lot width of 110 feet.
December 17, 2025 - The applicant held a neighborhood meeting in League City. The sign-in sheet indicates that three members of the public attended the meeting.
December 31, 2025 - The applicant submitted the PUD Amendment request to the Planning Department.
January 26, 2026 - Public hearing notices were mailed to the surrounding property owners and published on the city’s website.
January 28, 2026 - A public hearing sign was posted on the property, and notice was published in the newspaper.
February 12, 2026 - Planning & Zoning Commission held a public hearing recommended approval of the request.
February 24, 2026 - City Council is scheduled to conduct a public hearing and consider the request on first reading.
March 24, 2026 - If approved on first reading, City Council will consider the second reading of the request.
Project Summary:
Under the original Duncan PUD, overhead power lines are limited to the perimeter of the development and the north south arterial, Landing Bo...
Click here for full text