Legislation Details

File #: 26-0500    Version: 1 Name: Replace Odor Control System DSWWTP
Type: Agenda Item Status: Consent Agenda
File created: 11/2/2026 In control: Public Works
On agenda: 11/17/2026 Final action:
Title: Consider and take action on a resolution authorizing an agreement with Vapex Environmental Technologies, dba Govapex for the replacement of the odor control system at the Dallas Salmon Wastewater Treatment Plant (DSWWTP) Lift Station in an amount not to exceed $124,000 (Director of Public Works)
Attachments: 1. Proposed Resolution, 2. Exhibit A - Agreement with Vapex Environmental Technologies, dba Govapex, 3. Sole Source Letter, 4. Vendor Report Card
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Consider and take action on a resolution authorizing an agreement with Vapex Environmental Technologies, dba Govapex for the replacement of the odor control system at the Dallas Salmon Wastewater Treatment Plant (DSWWTP) Lift Station in an amount not to exceed $124,000 (Director of Public Works)

Background:
Approval of this item will authorize an agreement with Vapex Environmental Technologies, dba Govapex for the replacement of the odor control system at the Dallas Salmon Wastewater Treatment Plant (DSWWTP) Lift Station in an amount not to exceed $124,000.

The existing system was installed in 2016 and is obsolete and beyond economical repair. The proposed replacement will consolidate the existing 3500 and Nano units into one Milli unit, reducing replacement costs. This system is needed to control hydrogen sulfide (H2S) levels and odors around the headworks and surrounding neighborhood.

Sole-source procurement is needed to obtain a direct-fit replacement from the existing manufacturer that uses the same odor control process and requires no modifications to the existing installation.

Pursuant to Texas Local Government Code § 252.022(a)(2) and (3), this procurement is exempt from the competitive purchasing requirements of Chapter 252 (2) a procurement necessary to preserve or protect the public health or safety of the municipality’s residents and (3) a procurement necessary because of unforeseen damage to public machinery, equipment, or other property.

Staff recommends approval of the replacement of the odor control system at the DSWWTP in an amount not to exceed $124,000.

Attachments:
1. Proposed Resolution
2. Exhibit A - Agreement with Vapex Environmental Technologies, dba Govapex
3. Sole Source Documentation
4. Vendor Report Card

FUNDING
{X} Funds are available as follows: Wastewater Department’s Utility System & Repair Account# 10207500-52620 ($124,000).

STRATEGIC PLANNING
{X} Addresses Strategic Planning Critical Success Factor #1 - Develop and ...

Click here for full text