Title
Consider and take action on a resolution authorizing a Professional Services Agreement with Sander Engineering Corporation for design, bid and award, and construction phase services related to the Hwy 3 Water Plant - 1 MG Ground Storage Tank Interior Recoating (WT1802D) in an amount not to exceed $87,600 (Executive Director of Capital Projects)
Background:
Approval of this resolution will authorize a Professional Services Agreement with Sander Engineering Corporation for design, bid and award, and construction phase services related to the Hwy 3 Water Plant - 1 MG Ground Storage Tank Interior Recoating (WT1802D) in an amount not to exceed $87,600.
The purpose of this project is to recoat the interior of the Hwy 3 Water Plant Ground Storage Tank and perform structural repairs.
Sander Engineering Corporation will provide Preliminary Design, Final Design, Contract Bid & Award, and Construction Administration Phase services, as summarized below:
Preliminary Design $ 28,500
Final Design $ 25,000
Contract Bid & Award $ 4,500
Construction Administration & Coating Inspection $ 28,100
Reimbursable Expenses $ 1,500
TOTAL $ 87,600
Design phase will be completed within 200 days, excluding City review and approval periods, followed by bid and construction phase.
Attachments:
1. Proposed Resolution
2. Exhibit A-PSA with Proposal
3. CIP Project Sheet
4. CIP Aerial Map
5. Vendor Report Card
FUNDING
{X} Funding in the amount of $87,600 is available from fund 1055, Revenue Supported Cash, with expenses charged to project expense string WT1802D-PLAN DESIGN-DESIGN-RS CASH.
STRATEGIC PLANNING
{X} Addresses Strategic Planning Critical Success Factor #1: Develop and Maintain our Infrastructure.