File #: 17-0426    Version: 1 Name: Texas Sterling Construction Co. for Calder Road Improvements Project
Type: Agenda Item Status: Approved
File created: 6/26/2017 In control: Public Works
On agenda: 7/11/2017 Final action: 7/11/2017
Title: Consider and take action on a resolution authorizing change order number 1 with Texas Sterling Construction Co. for the Calder Road Improvements Project (ST1002) to increase the contract amount by $129,240.24 (Director of Public Works)
Attachments: 1. Data Sheet, 2. Proposed Resolution, 3. Exhibit A - Change Order No. 1
Title
Consider and take action on a resolution authorizing change order number 1 with Texas Sterling Construction Co. for the Calder Road Improvements Project (ST1002) to increase the contract amount by $129,240.24 (Director of Public Works)

Background:
Approval of this resolution will authorize change order number 1 in the amount of $129,240.24 for the construction of the Calder Road Improvements Project.

On September 13, 2016, City Council awarded the construction contract for the Calder Road Improvements Project to Texas Sterling Construction Co. in the amount of $7,528,129.70, and authorized a work change directive budget of $752,812.97. The work change directive budget is to be used for minor work changes and change orders that will adjust the contract price and contract time to reflect conditions that unexpectedly arise because of the actual construction development of the project.

Change order number 1 represents an increase to the contract in the amount of $129,240.24. The individual change order items are as follows:

1. WCD No.1 - The installation of an interim Traffic Control Plan (TCP) to maintain ONE WAY traffic, from Oleander Street to League City Parkway. This interim TCP included moving traffic from the west side of the road to the east side of the road. The interim TCP was required because the west side of the road was badly damaged during heavy construction activity in the area and it was not reasonable to return Calder Road back to TWO WAY traffic for the short period between the Sanitary Sewer Project completion and the Calder Road Street Improvements Project (increase amount of $12,816).
2. WCD No. 2 - This included the addition of two-months of interim TCP to facilitate utility relocation, and modifications to the interim TCP to allow TWO WAY traffic from League City Parkway to Turner Road to facilitate the new retail businesses (increase amount of $9,492.24).
3. The Calder Road Construction Traffic Control Pl...