File #: 18-0561    Version: 1 Name: PH - TX Parks/Wiildlife grant Bayridge Park
Type: Agenda Item Status: Public Hearing
File created: 9/12/2018 In control: Parks & Cultural Services
On agenda: 9/25/2018 Final action:
Title: Hold a public hearing on the submission of a grant application to the Texas Parks and Wildlife Department for a 50%/50% City/State matching grant supporting the Bayridge Park Redevelopment Project (PK11), due to be submitted on or before October 1, 2018 (Director of Parks and Cultural Services)
Attachments: 1. Data Sheet, 2. Proposed Site Plans, 3. CIP and Aerials documents, 4. Highlights of TPWD Grant

Title

Hold a public hearing on the submission of a grant application to the Texas Parks and Wildlife Department for a 50%/50% City/State matching grant supporting the Bayridge Park Redevelopment Project (PK11), due to be submitted on or before October 1, 2018 (Director of Parks and Cultural Services)

 

Background:

Staff is applying for the Texas Parks and Wildlife Department (TPWD) Outdoor Recreation Grant which is due October 1, 2018 and requires a public hearing to provide citizens an opportunity to comment on the plans. Bayridge Park is one of the older parks in the City of League City park system. It is identified in the Parks, Trails, and Open Space Master Plan as a priority for an upgrade. Currently the CIP calls for $100,000 in Park Dedication Funds. The grant will provide funding for additional improvements to the park.

 

The Texas Parks and Wildlife Department (TPWD) manages the Local Park Grant Program, funded by a State-wide Sporting Goods Tax, and provides funding for acquisition of land and new constructions and major renovations to existing parks and trails. The maximum amount of funding that TPWD will award is $500,000, or 50% of the project total with the City of League City being required to match the same amount in dollars or in-kind (land, labor, materials, or equipment usage).

 

For the City's 50% match, it is proposed to utilize the following funding sources:

 

1.  The value of the unopened street right-of-way adjacent to the park, estimated at $250,000 (the land would then become a part of Hometown Heroes Park and a portion of the 5K Trail will run within that corridor)

 

OR

 

2.  A total of $500,000 from the current $1,200,000 that is budgeted for construction of the 5K Loop Trail in Hometown Heroes Park.  By utilizing the $500,000 in 5K Loop Trail funds, the full $500,000 used as a match will continue to be applied for constructing the 5K Trail project and will be matched by TPWD with $500,000.  This will be divided as follows: approximately $200,000 for an additional trail or trail amenity construction in Hometown Heroes Park and $300,000 in amenities and professional services within Bayridge Park

 

OR

 

3.  A combination of the two (2) matching fund sources listed above to reach the $500,000 match required by TPWD

 

 

TPWD Grant                                                                                                                                                                                                                                       

$300,000:                     Bayridge Project                                                                                                                                                                                              

$200,000:                     5K Loop Project                                                                                                                                                                                                                  

$500,000                                                                                                                                                                                                                                                                                 

 

Funding for Bayridge Project

$100,000:                     Park Dedication Fund

$300,000:                     TPWD Grant

$400,000

 

Budget for Bayridge Project

$53,000:                     Design FY2019

$347,000:                     Construction FY2021

$400,000

 

The grant application process also requires a public hearing to be conducted by the grantee (the City of League City) to solicit input from the public concerning the grant application and the new construction that will take place. TPWD also requires that a resolution be adopted by the City Council and that a staff member or elected official be designated as a representative of the City to handle correspondence with TPWD and other official business related to the project.

 

Attachments:

 

1.  Data Sheet

2.  Proposed Site Plans

3.  CIP Sheets and GIS Aerials

4.  Highlights of TPWD Grant

                                     

FUNDING

{x} NOT APPLICABLE

 

STRATEGIC PLANNING

{x} Addresses Strategic Planning Critical Success Factor # 4 and Initiative # 6, Action Item E