File #: 19-0547    Version: 1 Name: RE1704E Asphalt Pkg 5 HR Green design
Type: Agenda Item Status: Approved
File created: 10/1/2019 In control: City Council
On agenda: 10/8/2019 Final action: 10/8/2019
Title: Consider and take action on a resolution authorizing a professional services agreement with HR Green, Inc. for design work related to the Asphalt Streets Rehabilitation Project Package 5 (RE1704E) in an amount not to exceed $211,952. (Director of Budget & Project Management)
Attachments: 1. Data Sheet, 2. Proposed Resolution, 3. Agreement with HR Green with Exhibit A Proposal, 4. CIP Project Sheet, 5. Aerial Map - Glen Cove, 6. Aerial Map - West Area
Title
Consider and take action on a resolution authorizing a professional services agreement with HR Green, Inc. for design work related to the Asphalt Streets Rehabilitation Project Package 5 (RE1704E) in an amount not to exceed $211,952. (Director of Budget & Project Management)

Background:
Approval of this resolution will authorize the award of a professional services agreement with HR Green to perform the engineering design and construction phase services related to package 5 of the Asphalt Street Rehabilitation Project (RE1704E).

The purpose of this project is to perform road base repairs, asphalt resurfacing, and full depth reconstruction as part of an annual infrastructure reinvestment program. Package 5 consists of North Wisconsin Ave and Wesley Street (between I45 feeder and FM518). Package 5 also consists of the following streets within the Glenn Cove Subdivision: Cove Park, Knollwood St., Mission St., Monterrey St., Redwood St., Rimrock St., Sequoia St., Shasta St., Sierra St., Winn St.; as well as Power St. (southeast of East Main Street and northeast of Dickinson Avenue). The approximate length of mill & overlay operations is approximately 10,581 linear feet and approximately 10,218 linear feet of full depth reconstruction. Preliminary construction cost for package 5 is $3,478,992.

For the Package 5 project, City Staff has inspected the proposed streets for repair and identified which streets need full depth reclamation and which streets just need mill and overlay. Similar to Package 4, the proofrolling has been increased to a 24-ton roller which will better identify potential weak spots.

HR Green has submitted a proposal to perform the engineering design and construction phase services not to exceed $211,952, which includes the following:
1. Design Phase $ 116,321
2. Bid-Phase Services $ 5,912
3. Construction Phase Services $ 6,377
4. Subconsulting $ 82,442
5. Direct Expenses $ 900
Total $ 211,952