File #: 24-0613    Version: 1 Name: Oaks of Clear Creek Detention Pond Improvements (DR2101B)
Type: Agenda Item Status: Consent Agenda
File created: 11/25/2024 In control: Capital Projects
On agenda: 12/17/2024 Final action:
Title: Consider and take action on a resolution authorizing an amendment to the professional services agreement with ARKK Engineers for the Oaks of Clear Creek Detention Pond Improvements (DR2101B) in an amount not to exceed $117,190 (Executive Director of Capital Projects)
Attachments: 1. Proposed Resolution, 2. Exhibit A - Fifth Amendment & ARKK Proposal, 3. Executed Original Agreement (ARKK), 4. Approved Amendment 1, 5. Approved Amendment 2, 6. Approved Amenement 3, 7. Approved Amendment 4, 8. CIP Project Sheet, 9. CIP Aerial Map(Modif.), 10. Vendor Report Card
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Consider and take action on a resolution authorizing an amendment to the professional services agreement with ARKK Engineers for the Oaks of Clear Creek Detention Pond Improvements (DR2101B) in an amount not to exceed $117,190 (Executive Director of Capital Projects)

Background:
Approval of this item will authorize an amendment to the professional services agreement with ARKK Engineers for the Oaks of Clear Creek Detention Pond Improvements (DR2101B) in an amount not to exceed $117,190.

On May 11, 2021, the Council approved a professional services agreement with ARKK Engineers for planning and design of the Oaks of Clear Creek Detention Pond Improvements in an amount not to exceed $423,020. Between mid-2021 and now City and consultant have completed surveying, geotechnical, environmental, engineering studies for pond location and improvements inside the neighborhood, and developed construction plans for proposed improvements. The site for the detention pond was also negotiated and acquired during this period. During this period four (4) amendments totaling $19,650, as shown below, were administratively approved.

The Federal Emergency Management Agency (FEMA) who is providing major grant funds for the project has requested a full Hydrologic and Hydraulic (H&H) analysis and report as well as a Benefit Cost Analysis (BCA) for the proposed drainage improvements in the Oaks of Clear Creek subdivision. The cost for the additional scope of work is in the amount of $117,190.

Summary of Fees:
Original Agreement: $423,020
First Amendment: $9,900
Second Amendment $0
Third Amendment $9,750
Fourth Amendment $0
Fifth Amendment $117,190
Total Amended Agreement: $559,860

Attachments:
1) Resolution
2) Exhibit A - Fifth Amendment & Proposal
3) Executed Original Agreement
4) Approved First Amendment
5) Approved Second Amendment
6) Approved Third Amendment
7) Approved Fourth Amendment
8) CIP Project Sheet
9) CIP Aerial Map (Modif.)
10) Vendor Repor...

Click here for full text