Title
Consider and take action on a resolution authorizing a construction contract with Jerdon Enterprise, L.P. for the FM 270 Public Boat Ramp Renovation Project (PK1804) in an amount not to exceed $1,835,039.05, authorizing an additional $183,503.00 for a Work Change Directive budget, and authorizing a construction material testing services with Geotech Engineering and Testing in an amount not to exceed $31,424.00, for a total construction project budget of $2,049,966.05 (Executive Director of Capital Projects)
Background:
Approval of this resolution will authorize a construction contract with Jerdon Enterprise, L.P. for the FM 270 Public Boat Ramp Renovation Project (PK1804) $1,835,039.05, authorizing an additional $183,503.00 for a Work Change Directive budget, and authorizing a construction material testing services with Geotech Engineering and Testing in an amount not to exceed $31,424.00, for a total construction project budget of $2,049,966.05.
The following is a summary of scope of work for this project:
1. Bulkhead Rehabilitation - Include new sheet piling and backfill.
2. General Site Improvements - Include sidewalk, parking lot improvements and bollards.
3. Walkway Rehabilitation and Extension - Extension of the raised wooden walkway as well as replacement of the decking/stringers. Enhancements including new dock bumpers and encasement of the timber piles in fiber reinforced plastic.
4. Boat Ramp Rehabilitation - Replacement of Ramp 2, extension of Ramp 3 and added scour protection to Ramp 1.
One (1) sealed bid was received on June 25, 2026 (Bid No. 26-036). Despite receiving only one bid, contractor is a responsible and responsive bidder:
1. Has recently completed City’s Nature Center Kayak Launch project successfully.
2. Amount of base bid is within engineer’s estimate, contract time is very reasonable, and
Prices on Alternates are all reasonable.
3. Contractor’s qualifications show successful projects completed for other municipalities.
4....